colibri Hangar Construction
Building our Hangar on Airport EDPW
In the end of 2010, we bought a steel hangar from EUSTEEL.AT, which was delivered in 2011. Since in 2011 we first had to build the gas station, we had to keep the different hangar parts stowed away until fall 2012.
In March 2012, the foundation was created by the Greding-based company Dollinger und Schneider.
In the middle of October 2012, we finally started putting up the hangar. Thanks to many hard-working helpers, it took only two weeks to build the hangar.
Approximately 6 hours of construction work summarized in a time lapse of 5-6 minutes.