colibri Hangar Construction

Building our Hangar on Airport EDPW

In the end of 2010, we bought a steel hangar from EUSTEEL.AT, which was delivered in 2011. Since in 2011 we first had to build the gas station, we had to keep the different hangar parts stowed away until fall 2012. 

In March 2012, the foundation was created by the Greding-based company Dollinger und Schneider.

In the middle of October 2012, we finally started putting up the hangar. Thanks to many hard-working helpers, it took only two weeks to build the hangar. 

 

Halle 01Halle 02Halle 03Halle 04Halle 05Halle 07Halle 10Halle 20Halle 30Halle 40Halle 50Halle 51Halle 51_400_250_0_23Halle 55Halle 6Halle 60Halle 70Halle 80Halle 90Halle 95Halle 97Halle 98Halle 99Halle 991Halle 992Halle 995Halle 996Halle 997Halle 998Hallehalle 96

 

Approximately 6 hours of construction work summarized in a time lapse of 5-6 minutes. 

youtube image youtube image

DFV - Deutscher Fallschirmsport Verband e.V.U.S. Parachute Association | Foreign Affiliate
Quick Question
I acknowledge the Privacy Policy, I agree to the storage of my data.

Imprint · Privacy Policy

skydive colibri · Skydiving · Flugplatz Waizenhofen 40 · 91177 Thalmässing · Fon 0 91 73 . 79 477 1 · Fax 0 91 73 . 79 477 2 · info(at)freifallen.de

Werbeagentur Augsburg eg media · made with Einfaches CMS

Unser Absetzflugzeug D-FLAC

Privacy Settings

This website uses cookies and exchanges data with partners. With further use, consent is given. Further information and adjustment of the settings at any time at our Privacy Policy.